Texas' environmental agency, the Texas Commission on Environmental Quality (TCEQ), has resumed reviewing the data center's environmental permits, ending a moratorium ordered by Governor Greg Abbott in September. according toTexas Tribune reported Nov. 17, a TCEQ spokesperson said the agency "has resumed normal permit review procedures."

But this release may not last long. New Democratic Governor Gina Hinojosa, who defeated Abbott on November 3, took office on January 19. During her campaign, she promised to ban all data center approvals after taking office until the state Legislature passes a new law.

The governor's office informed that the power grid information had been collected, and the Environmental Protection Agency immediately released it.

The Texas Tribune pointed out that TCEQ received notification from the governor’s office on November 13 (Friday) that the Texas power grid operator ERCOT had completed the collection of data on the impact of the data center on communities. This is one of the matters that Abbott asked the power grid and power regulators to evaluate. TCEQ is responsible for the air pollution permit and construction site runoff permit for the data center.

Environmental groups are not footing the bill. Consumer rights organization Public Citizen criticized that ERCOT's evaluation results were not announced to the public, and TCEQ did not explain how it would be used in the review, but began to issue permits on its own, and asked the TCEQ commissioner to step down.

The moratorium began in August over 474 GW of power applications

In August, Abbott asked the Public Utility Commission of Texas (PUCT) and ERCOT to audit all data centers that were applying for grid connection. ERCOT immediately postponed the "Batch Zero" grid connection review process for large power users. according to Utility Dive ReportAt that time, the electricity demand queued for grid connection was estimated to be 474 GW. Abbott said in the letter that the scale of the data center development "may jeopardize the reliability and stability of the Texas power grid."

Abbott, September 21 Then order TCEQ Stop issuing all data center permits until ERCOT completes the audit: "Simply put, Texans must put first." He requires data centers to bear the cost of their own power facilities, not to use water needed by local communities, and to report electricity and water consumption. In October, an environmental group discovered that there were still permits related to the data center that had passed the inspection. TCEQ once shut down the entire online application system and switched to paper copies.

Next key dates

The Texas Tribune and Law Firm Timeline compiled by Gibson Dunn, the audit is not over yet, the policy may also be reversed after the new governor takes office:

Date event December 10, 2026 (target) ERCOT submits two reports to PUCT to determine which large power users over 75 MW remain in Batch Zero and compiles water, power and community impact data from the data center December 17, 2026 (estimated) PUCT public meeting to discuss audit report January 19, 2027 Hinojosa takes office, can revoke or rewrite Abbott's executive order, and appoint PUCT and TCEQ commissioners when commissioners' terms expire April 9, 2027 ERCOT has said it cannot meet the current deadline for Batch Zero study results and expects an extension

Gibson Dunn noted that Abbott's moratorium is a gubernatorial directive, not a regulation or law, and only binds the current administration. "When I become governor, I will issue a ban on all data center certifications until the Legislature passes a law that protects Texans," Hinojosa said in an Oct. 22 video on X, where she will face the Democratic-majority state House of Representatives.

this article Texas resumes review of data center licenses, and the new governor took office on January 19th threatening a complete shutdown first appeared in Chain News ABMedia。